The 2nd of the Eastern Siberia – Pacific Ocean Oil Pipeline (ESPO II), constructed and operated by Transneft, was commissioned on December 25, 2012 with Argosy's help.

In 2011-2012, Argosy manufactured and supplied complete measurement systems for Transneft facilities, supervised equipment installation, start-up and successfully commissioned two large scale oil metering stations:

  • Custody transfer measurement skid at Skovorodino oil pumping station 21. The skid is installed at the ESPO II inlet.
  • Custody transfer fiscal skid at station 922 at Kozmino Bay oil terminal. The system is installed at the ESPO II outlet.

Argosy Contributed to Successful Commissioning of the Second Stage of ESPO Oil Pipeline

Argosy Contribution to Successful Commissioning of the 2nd of the ESPO Oil Pipeline has been awarded by Transneft.

The custody transfer fiscal skids used at ESPO II are produced by Argosy.